HV lines
Dětmarovice
110 kV Line Construction
Timeline
11/2023 – 12/2024
Contract value
EUR 7.3 m
Voltage level
110 kV
Completion
2024 ✓
Scroll down ↓
5,757m
110 kV cable lines
11pcs
New 110 kV towers
1,775m
Phase conductors and OPGW
110kV
Voltage level
Laying of two new 110 kV cable lines connecting the Dětmarovice Power Plant with the ČEZ Distribuce substation, including the optical link, construction of new towers and installation of a new OPGW.
The cable section comprised laying two new 110 kV lines — V5689, 2,988 m long, and V5690, 2,769 m long, i.e. 5,757 m of cable in total — including the optical link between both sites.
At the same time, 11 new 110 kV towers were built, new phase conductors were strung and a new OPGW was installed on sections V691/692 (886 m) and V693/694 (889 m). The contract was completed in December 2024.
Technical specification
Project parameters
Delivery period
11/2023 – 12/2024 (completed)
Contract value
EUR 7.3 m
Voltage level
110 kV
Cable lines
V5689 — 2,988 m · V5690 — 2,769 m (5,757 m in total)
Towers
11 pcs new 110 kV towers
Conductors and OPGW
V691/692 — 886 m · V693/694 — 889 m
Scope of supply
Laying of 110 kV cables (5,757 m in total)
Construction of 11 new 110 kV towers
Installation of phase conductors and OPGW
Optical link
Photo documentation
From the project
Cooperation
Ready to start
Ready to start
your project?
Contact us to discuss cooperation. We deliver projects in the Czech Republic and abroad.
Pavel Pavlátka
Managing Director