HV lines

Dětmarovice
110 kV Line Construction

Timeline
11/2023 – 12/2024
Contract value
EUR 7.3 m
Voltage level
110 kV
Completion
2024 ✓
Scroll down ↓
5,757m
110 kV cable lines
11pcs
New 110 kV towers
1,775m
Phase conductors and OPGW
110kV
Voltage level

Laying of two new 110 kV cable lines connecting the Dětmarovice Power Plant with the ČEZ Distribuce substation, including the optical link, construction of new towers and installation of a new OPGW.

The cable section comprised laying two new 110 kV lines — V5689, 2,988 m long, and V5690, 2,769 m long, i.e. 5,757 m of cable in total — including the optical link between both sites.

At the same time, 11 new 110 kV towers were built, new phase conductors were strung and a new OPGW was installed on sections V691/692 (886 m) and V693/694 (889 m). The contract was completed in December 2024.

Technical specification

Project parameters

Delivery period 11/2023 – 12/2024 (completed)
Contract value EUR 7.3 m
Voltage level 110 kV
Cable lines V5689 — 2,988 m · V5690 — 2,769 m (5,757 m in total)
Towers 11 pcs new 110 kV towers
Conductors and OPGW V691/692 — 886 m · V693/694 — 889 m
Scope of supply Laying of 110 kV cables (5,757 m in total) Construction of 11 new 110 kV towers Installation of phase conductors and OPGW Optical link
Photo documentation

From the project

Dětmarovice 110 kV line construction 110 kV cable laying 110 kV tower erection 110 kV line route